The night's objective? To dismantle four imposing 40-metre-high concrete lighting poles dating from the 1970s, whose stability was no longer guaranteed. A fine challenge, since time was of the essence: as soon as the first colors of dawn appear, the E40 is invaded by commuters...
So it took our colleagues and subcontractor teams 4 nights to disconnect the power grid, cut each pole into sections, and finally truck them away. And because sustainability is at the heart of our activities, the sections were then taken to a waste management center to be crushed and reused as construction aggregate
Improving the Belgian (and global) electricity grid is at the heart of the energy transition to ensure better quality, more sustainable electricity.
And we're proud to be part of it, day and night!
-
02.09.2024Charging stations at Blagnac airport : a 100% green...Eiffage Énergie Systèmes has undertaken civil and electrical engineering work for a charging station at Toulouse-Blagnac airport on behalf of its customer Electra. ...
-
05.08.2024Eiffage Énergie Systèmes installs EVCS for Powerdot...Powerdot and Fastned are two European operators specializing in the installation of Electric Vehicle Charging Stations in supermarket car parks and motorway service...
-
16.07.2024Eiffage Énergie Systèmes strengthens its presence in...Eiffage Énergie Systèmes, through its Dutch subsidiary Eiffage Energiesystemen1, just acquired EKB and recently took a majority stake in Rensen Regeltechniek.